York has added £2.5m of road and pavement repairs this year. The council paper names every street: Hull Road, Tang Hall Lane, Lindsay Avenue, the A1237 and more.

York has added just over £2.5 million of road and pavement repairs to this year’s programme. The biggest single sum, £400,000, goes on resurfacing the A1079 Hull Road between Kexby and Dunnington.

City of York Council announced the extra schemes today. Its release named only areas. The officer decision behind it, signed on 22 October, names every street and the budget for each. It is published on the council’s decision register.

The money comes from the York and North Yorkshire Combined Authority. Its cabinet confirmed the Mayoral Transport Fund on 2 October, months after the council had set its own budget. The council’s addendum report says the late confirmation is why some schemes were extended before the paperwork caught up.

The money in three pots

Programme Budget
Mayoral Road Maintenance Fund (main roads) £1,100,000
Highway schemes £926,125
Pavement and active travel schemes £502,784
Total £2,528,909

The report says these schemes take “the majority of the £2.6m” of extra funding. Anything left over goes into the existing 2026/27 programme.

Main roads: £1.1 million

The Mayor asked for this fund to be spent on the strategic network. The schemes are:

Scheme Budget What it is
A1079 Hull Road Phase 2 (Kexby to Dunnington) £400,000 New resurfacing scheme
A1237 at the Askham Bryan / Moor Lane roundabout £127,000 New scheme after further survey
Jockey Lane £126,500 Extension of this year’s scheme
A1237 east of the A19 roundabout £94,500 New resurfacing scheme
A1237 at the Little Hopgrove roundabout approach £86,000 New scheme after further survey
A19 patching £80,000 Extension of this year’s scheme
A1079 Hull Road Phase 1 £80,000 Extension of this year’s scheme
A1237 at the A19 roundabout, west approach £66,000 New scheme after further survey
Lendal Bridge £40,000 Emergency repair after further survey

Residential roads: £926,125

Scheme Budget What it is
A1079 Hull Road, Beeswing to Tang Hall Lane £352,750 Resurfacing
Lindsay Avenue £152,000 Resurfacing
Outgang Lane £111,125 Resurfacing
Tang Hall Lane, St Hilda’s Mews to Fifth Avenue £108,250 Resurfacing
Elvington Lane £102,000 Drainage improvements
Philadelphia Terrace £100,000 Resurfacing

Pavements and crossings: £502,784

Scheme Budget
Fifth Avenue, Sixth Avenue to Fourth Avenue £161,600
Lindsay Avenue tactile crossings £132,000
Keble Park Crescent £100,000
North Lane, Wheldrake £74,552
Delwood £34,632

Lindsay Avenue gets work on both lists, £284,000 in all. Tang Hall gets the road from St Hilda’s Mews to Fifth Avenue and the Fifth Avenue pavements.

What the council and the Mayor said

Councillor Kate Ravilious, the executive member for transport, said: “This has been made possible by the confirmation of funding at a recent Combined Authority Meeting, and we’re acting quickly to get these repairs planned in and completed as soon as possible.”

David Skaith, Mayor of York and North Yorkshire, said the money “gives City of York Council the certainty to act quickly, plan for the future and fill more potholes across the city”.

The backlog behind it

The extra money is small against the size of the problem. The addendum report puts the backlog at £102 million to bring every highway asset in the city to perfect condition.

The council looks after:

  • 800km of roads
  • 1,000km of footways
  • 250km of walking and cycling paths

The Department for Transport’s new rating system gave York amber overall, like most authorities, the report says. York scored green for the extra money it puts in on top of its core funding, and amber for asset condition and best practice.

What it means for you

  • No dates yet. The decision does not schedule the works. The report says the programme is meant to be delivered before the end of the financial year, 31 March 2027.
  • You will get a letter. The council’s planned highways works page says consultation letters go to residents on every affected street before work starts.
  • Some of it may already be done. The report says some main-road extensions were carried out before the funding was confirmed. The council’s release names the recent stretches on the A19 south of Fulford and the A1079 as examples of longer resurfacing.
  • Report a pothole through the council’s road and pavement problem form.

Closures will appear on our York roadworks page once dates are set. The A1079 Phase 1 works are covered in our September story.