A council report says York Station Gateway substation works are on hold over Network Rail issues. A petition for a cost breakdown has 1,759 signatures.

Substation works at York station are “currently on hold / in delay”, leaving part of the Station Gateway scheme unfinished. A council report to Executive on 3 November blames re-design, approvals and insurance cover issues that need resolving with Network Rail.

It says the substation “may not be completed until later in 2026”.

Meanwhile, a Change.org petition calling for a full explanation of the scheme’s cost had 1,759 signatures when we read it on 5 November. It was started on 1 August.

What is unfinished

The report says the carriageways, new bus stops, laybys and pedestrian crossings are all operational. The cycleways were “due to be substantially open at the end of September”, though the report gives no later update on that.

The old substation is what holds up the rest:

  • one stretch of cycleway on the station side cannot be finished until it is removed
  • there will be “an extended period of incomplete works” on the station frontage behind the bus shelters
  • an interim package of works, including a new fence line, is needed in the meantime
  • later work includes demolishing the substation and building a cycleway on a temporary alignment

The report says scope has changed and some work has been reordered between this stage and the next, Package 3, the station works. It adds that “additional time and works” are being monitored. These paragraphs put no cost on them.

What the petition asks

The forecast cost is £60.104m against an original £26m, as we reported in August from the council’s own papers. The petition asks the council to:

  • publish a detailed breakdown of how the cost grew
  • explain the key decisions behind the increase
  • publish what it is doing to carry out the recommendations of the independent audit
  • strengthen financial oversight of future major projects

The report does not mention the petition or set out a new total. Annex 1 shows £29.479m still budgeted for the scheme: £10.483m this year, £8.789m next year and £10.207m in 2028/29. We have not seen a published council response to the petition, and the petition page shows none.

What it means for you

  • Station users: expect fencing and unfinished works behind the bus shelters to stay for longer.
  • Cyclists: one section on the station side will stay incomplete, then run on a temporary route.
  • Council tax payers: the £29.479m is a budget, not a final bill. The next capital monitor is the place to look for any change.

Travel disruption around the station is on our roadworks and travel page.