A council report expects the new station at Haxby to open in the 2028/29 financial year, with a planning decision this winter. It now calls it Haxby York North.

The new railway station at Haxby is expected to open in the 2028/29 financial year, which runs from April 2028 to March 2029. That is the estimate in a capital programme report to City of York Council’s Executive on 3 November.

The report says the timetable was prolonged by earlier uncertainty over funding. A planning decision on Network Rail’s application is now expected in winter 2026, after delays caused by that uncertainty and by further surveys for protected species.

The council’s own Haxby station page says the station should be “built and operational during 2028”, subject to planning.

A new name in the paper

The report heads the project “Haxby York North Station (formerly Haxby Station)”. The council’s project page still calls it Haxby Station, and we found no announcement explaining the change. Treat the name as provisional until the council or Network Rail announces it.

Who is doing what

Network Rail now leads delivery, with the Department for Transport as scheme promoter. The council and the York and North Yorkshire Combined Authority are supporting.

The council still owns the freehold of the site. It is responsible for the highway works and for road safety and active travel measures around the station.

The September report expected those road works in 2027. The new one says the 2027/28 financial year, with some preliminary works this year.

Council budget for the station (Annex 1) Amount
2026/27 £169,000
2027/28 £1,371,000
2028/29 £2,220,000
Total £3,760,000

What is planned

According to the council’s project page, the planning application includes:

  • step-free access throughout, with a footbridge, lifts and steps between the two platforms
  • a 154-space car park with electric vehicle charging
  • bike shelters, a taxi rank and a bus stop
  • shared-use paths to Swarthdale and Usher Park Road, and along Towthorpe Road

The original Haxby station closed in 1930.

What it means for you

  • Commuters: the estimate points to some time between April 2028 and March 2029. It depends on planning permission.
  • Neighbours of the site: the planning decision is the next step, expected this winter.
  • Drivers: road works around the site are now a matter for 2027/28, not this year, beyond preliminary work.

Separate plans for the village centre are out to consultation until 9 December: see what is proposed for Haxby and Wigginton.

The Executive’s decisions from 3 November had not been published when we checked this afternoon.

Sources